Tigo EI Inverter Manual

Installation manual for the Tigo EI Inverter, including instructions for the EI Battery, ATS, and Energy Meter

DC Conduit

Thank you! Your submission has been received!
Oops! Something went wrong while submitting the form.

Supplies needed: 1” conduit and associated fittings.

The left DC conduit opening (5) is reserved for the inverter’s PV input conductors for connection to the PV array. This conduit hole should have been opened prior to mounting the inverter. If not, make sure the inverter is securely mounted and the cover removed before drilling open the conduit drill guide and use caution to not come in contact with any internal components.

Route the conduit between the inverter and the PV array. Use appropriate conduit fittings to ensure a water-tight seal. Bond any metallic conduit, as required.

The right DC conduit opening (6) is reserved for the DC battery input conductors which connect to the EI Battery in battery installations. If installing the EI Battery, route the conduit from the right conduit opening to the EI Battery. Use appropriate conduit fittings to ensure a water-tight seal. Bond any metallic conduit, as required.

Conductor preparation

Tools required: wire cutter, wire stripper, crimping tool, conductor labels/marking method

Supplies needed: AC conductors, wire ferrules (L)

The DC power conductors are terminated in the EI Inverter via pressure terminals. These terminals clamp on to the exposed end of the conductor. To ensure a reliable connection always use wire ferrules (L) on the end of these conductors.

1) Run the DC conductors and EGCs through the appropriate DC conduit.

2) Strip 5/8in (16mm) of insulation from the end of the PV+, PV- conductors. If installing an EI Battery, strip 0.7in (18mm) of insulation from the end of the BAT+ and BAT- conductors.

3) Use the crimping tool to connect the wire ferrules (L) to the conductor ends that will be terminated in the EI Inverter.

4) Label all conductors.